Great Adventure & Safari, New Jersey
 

Construction is complete and The Dark Knight Coaster is now open.  Our new indoor dark coaster is based on Warner Bros. Pictures' upcoming movie The Dark Knight, featuring
DC Comics' characters Batman and The Joker. See how construction progressed on
The Dark Knight Coaster

April 7, 2008





Installation of the thematic elements begin.




Track installation and support continues.











 

March 21, 2008





Track construction begins.











 

March 12, 2008





Frame work begins on the pre-show areas.






March 5, 2008





Construction crew begins to install wall panels on The Dark Knight Coaster building.





Ground work laid for pre-show areas.






February 26, 2008





Construction crane lowers steel beams onto the top of The Dark Knight Coaster to finish the roofing support.









Lateral supports and steel framing nears completion.





February 15, 2008






Second level of the frame begins to be erected.





February 7, 2008





Construction crew installs steel girts to support the frame of The Dark Knight Coaster building.





First level of the building's frame is erected. Currently stands approximately 4.5 stories - will be 7 stories at completion.






Boxes containing the coaster's cars arrive.





February 5, 2008





Building supports are laid out, ordered and grouped for ease of construction.





Steel supports begin to be erected to frame the first half of The Dark Knight Coaster building.














January 28, 2008





Electrical conduit installed for computer control room.





Concrete floor laid and leveled.









Concrete sealer applied to prevent cracks and reduce wear.









Second shipment of track received, including base of lift.






January 15, 2008





First shipment of track and ride support pieces arrive on a snowy January day.



























Conduit begins to be laid for electrical wiring.









Drainage pipes are installed around The Dark Knight Coaster  site.









Building foundation is completed and crew begins to level the ground for concrete floor.





January 2, 2008





Construction crew evens out the wet concrete on the footings.





Wooden barriers are removed from the first layer of dried concrete and new barriers are beginning to be built for second layer.




December 27, 2007





Wooden barriers constructed for the Concrete footings of The Dark Knight Coaster.





Metal re-enforcement bars are erected inside footing barriers for added support.





First layer of concrete for the footings begins to be poured.





December 3, 2007





Demolition of the Batman & Robin: The Chiller coaster nears completion.





Demolition of The Movietown Water Effect clears way for The Dark Knight Coaster .





Batman & Robin: The Chiller
foundation pier caps and anchor bolts are lined up for removal.